Left/ Main Frame & Grate Plate Fabrication2021-11-23T04:27:35+00:00

Project Description

Client: Gonzales Vietnam Company Limited.
Contractor: Minh Viet Engineering & Construction JSC.
Project Name: Fabrication of Left/ Main Frames, Wig-Wag Support, Grate Plates & End Stop.

Finished cutting. Drilling & Taping on progress.

Delivered

5086/ Left/ Right Frames & Wig-wag supports

Fabricate U-profiles.

Welding & Grinding works

Inspection after welding.

Repairing deformation of top plate.

Fit up Left/ Right frames.

Process drilling & taping.

Finished welding

Nearly finish drilling & taping.

CNC Taping Base plates thickness. 25mm.

Fit up Wig-Wag support frames.

Welding Wig-Wag support frames.